Stop Consolidation Plan Phase 3
• What is the stop consolidation project?
In 2009 the Spokane Transit Authority (STA) began work on a comprehensive look at the current placement of bus stops and transit amenities for frequent service routes. Completed in September 2010, Phase I of the Stop Consolidation Plan evaluated what stops should be removed and what transit amenities should be included for the frequent service routes. Phase III of the Stop Consolidation Plan continues the process of reviewing the placement of existing stops and amenities. In order to improve service efficiency and contain costs, STA will begin the third phase of the Draft Stop Consolidation Plan in July 2012.
• Why are we consolidating the number of bus stops?
The STA Board of Directors adopted the Service Design Guidelines which include a Stop Spacing and Placement Policy which states stops should generally be no closer than 800 feet, no further than 1,500 feet, and on average, a quarter mile apart.
• Stop consolidation will enable Spokane Transit Authority (STA) to:
- Improve travel speeds for Fixed Route buses
- Reduce travel time for passengers onboard Fixed Route buses
- Allow more bus stops to be placed near crosswalks and signalized intersections
- Reduce maintenance costs attributed to frequent stopping and starting of Fixed Route buses
• What are the dates for the actions of Stop Consolidation Phase III?
|
Date: |
Description: |
Comments: |
|
July 8th – July 29th |
Stop Closures notices posted at all stops proposed to be closed |
Public Comment accepted through July 29th |
|
Week of July 29th |
Stop Consolidation – Phase III plan finalized and final notices posted at all affected stops |
|
|
August 19th – September 16th |
Stops to be closed will be removed from service |
|
• What routes will be affected in Phase III?
The following routes have proposed stop plans for public comment. Please click the links to view maps of the routes with their associated stop changes as proposed.
In addition to the maps available on the website, customers may contact our hotline at (509) 343-1653 to request a copy of the materials regarding the Stop Consolidation Project.
• How can I give my input?
By contacting Mike Hynes - Transit Planner at (509) 325-6059 or via email at mhynes@spokanetransit.com.
• Will you look at other routes in the future?
STA strives to continually improve service for the rider and operate in a more efficient manner. As such, additional routes will be considered for Stop Consolidation. STA will seek public comment to assist with developing the final plan.